Before the First Hammer Falls…

What does it take to turn an ordinary 1930s house into a model for sustainable living? In the second of our four-part series, we follow the planning of Greville House, from ambitious first ideas to difficult decisions about cost, design and construction.

In the beginning was an unassuming semi on an ordinary street…


It was a perfectly ordinary home and that was the point. Its Energy Performance Certificate gave it a rating of D, typical of many British houses. It had three bedrooms, solid brick walls, double-glazed windows and a gas boiler. It also had an aging interior, a cramped kitchen and floor joists damaged by an old leak.

The Cambridge Retrofit team wanted to find out just how much an ordinary house could be improved. Could it be made to use a fraction of its former heating energy? Could it be comfortable in summer and winter, with fresh air, renewable power and less dependence on mains water? And could the work be done in a way that other people could learn from? The ambition was simple. Getting there would take years of planning.

Passivhaus, developed in Germany, is a rigorous approach to building design. It aims to create homes that need very little energy for heating or cooling. It relies on excellent insulation, airtight construction, high-performance windows and carefully controlled ventilation. All these things work together, resulting in a home that is warm in winter, comfortable in summer and economical to run.

But achieving Passivhaus-level performance in an existing building is not the same as designing a new one. Old walls, foundations, roofs and neighbouring properties impose limits. Every improvement must work around what is already there. There is a Passivhaus standard specifically for retrofits, called EnerPHit. It sets demanding targets for energy performance. The question was whether Greville House could meet those targets without costs becoming prohibitive.

A feasibility report, completed in December, compared several approaches, including EnerPHit, the AECB CarbonLite Retrofit Standard and guidance from LETI, a network concerned with improving the environmental performance of buildings. The AECB standard was ultimately chosen because it offered a more practical target. It was less demanding than EnerPHit but still required a substantial improvement in energy efficiency. This allowed the team to aim high without defaulting to the most expensive solution to every problem.

The architects used the “Passive House Planning Package”, or PHPP, to model the house's existing heat losses and estimate the benefits of different improvements. Their initial model estimated an annual space-heating demand of around 210 kilowatt-hours per square metre.

With proposed insulation to the walls, floor and roof, together with replacement windows and doors, that figure fell to approximately 36.5.

This demonstrated that a substantial reduction was possible and that the proposed scheme could achieve the AECB CarbonLite Level 2 Retrofit Standard. Plans were prepared for submission to the council to obtain permission for external wall insulation.

By early 2024, the project had evolved from a pie in the sky to a bun in the oven. It now had technical specs and a formal architectural design. But the drawings were only the beginning. A decision was made to change the interior layout. The small kitchen would be replaced with a more open arrangement. The house needed modern bathrooms, accessible spaces, and room for new heating and ventilation equipment.

Throughout this process, every part of the building had to be considered as part of a single system. For example: Insulating a wall is straightforward in principle. But what happens where that wall meets the floor? Or the roof? What happens around a window frame? These junctions can create thermal bridges, places where insulation is interrupted and heat escapes more easily through a building's structure.

Moving the windows outwards towards the new external insulation would help reduce these losses. But that created other questions about how the windows would be supported, sealed and protected from rain. The same problem appeared at the base of the walls. Insulation had to reduce heat loss without trapping moisture or exposing vulnerable materials to splashing rain.

Even the existing concrete fireplace hearths needed attention because they could carry cold through the newly insulated floor. Each decision affected another.

And a house designed to be airtight must also have reliable ventilation. Otherwise, moisture and indoor pollutants can accumulate. The team therefore planned a mechanical ventilation system with heat recovery, known as MVHR, alongside the insulation and airtightness work.

The aim was not just to improve the individual parts of the house. It was to make sure they all worked together.

By the summer of 2025, the plans were becoming much more detailed. The original feasibility study had considered double-glazed windows. The later specification called for triple glazing.

The external walls were to be wrapped in woodfibre insulation. The loft would use substantial amounts of local hemp insulation, alongside displays of other materials for training purposes.

The ground floor needed rebuilding and insulating. The team had to balance insulation depth, floor levels and wheelchair accessibility.

The team decided on an air-source heat pump, underfloor heating downstairs, and radiators upstairs. Solar panels, battery storage and external shading were incorporated into the design, along with a rainwater harvesting system. Some decisions were driven by energy performance. Others were about cost, safety, access, or practicality.

The house was intended to be used for education. The loft, for example, would need a strengthened viewing platform so visitors could see different insulation materials safely.

And the design had to consider its possible use as shared accommodation, bringing additional fire-safety requirements into the specification.

In September 2025, the passive house and retrofit specialists were still resolving technical details like how the floor insulation would connect to the walls, where moisture-resistant insulation should replace woodfibre near ground level, and which membranes would protect the building from unwanted air movement. They also had to figure out how to support windows and door thresholds without creating unnecessary heat loss. Some specialist materials were expensive so they tried to use them where they really mattered, not simply everywhere. Even the thickness of the external wall insulation was still under discussion as the team worked to balance thermal performance, practical installation and cost.

It was painstaking work. But these decisions would determine whether the finished building performed as intended. By the winter of 2025, Greville House had a substantial working design, supported by architectural drawings, energy modelling and an extensive technical specification. There were still details to resolve and decisions to refine, and even now, in the midst of building works, the team continues to problem solve, balancing the Passivhaus ideal against practical and financial realities.

Next in the series: Back to Bare Walls: The Hidden Work of Making a House Efficient.

We follow the builders as they strip back Greville House, confront the problems hidden inside its ageing structure and begin the work of turning years of planning into a low-energy home.

Follow the Greville House story: Sign up for the Cambridge Retrofit Hub newsletter to follow the transformation. If you're thinking about improving your own home, find out about our initial retrofit consultation.